MTU 4000 Hydraulic starting systems

Coral North is a conventional gas development located in ultra-deepwater in Mozambique and is operated by Mozambique Rovuma Venture. In collaboration with its client, Hatraco designed, produced and supplied 3x Hydraulic start systems which is destined for a FPSO in the Coral gas field in Mozambique.

The start systems are going to be used as the secondary startsystem for a fire water pump application. As per NFPA-20 requirements for a secondary start system, the start system provides the minimum of 6 times of 15 seconds of start duration. By means of pre-set pressure values, the hydraulic start system is automatically recharged by means of an electric motor driven recharge pump. The recharging cycle is managed by a pressure transmitter in combination with a PLC based control panel.  All of Hatraco's hydraulic start systems are equipped with a manual operated hydraulic pump as well. This enables our clients even to re-charge the system in a black out situation.


TECHNICAL INFORMATION
Project:Coral North
End user:Eni / Exxon mobile
Location:Coral Gas Field, Rovuma Basin, Cabo Delgado Province, Mozambique
EPCC:SHI / Tecnip /JGC
Start capacity:6 x 50 Liter
Start requirements :6 times 15 seconds each
Recharge time:within 30 minutes
Engine:MTU 4000
Required engine firing speed  :110 - 120 RPM
Application:MTU 4000 diesel engine driven fire water pump
Design code / Certification   :Accumulator design according to  ASME VIII Div 1, U stamped, Loyds register certified
Specialties:2 start valve manifolds for individual accumulator depletion
  Skid frame modified to enable a horizontally accumulator removal
  Skid contruction welding acc. to AWS D1.1. including weld book, WPS, WPQT, NDE