MTU 12V4000 Hydraulic start systems

Petronas FLNG 3, or ZLNG, is an (under-construction) floating facility in the Sabah region. It will be Petronas's third offshore facility after PFLNG 1 and PFLNG 2. The liquefaction facility will be located near Sipitang and will have a capacity of 2 mmtpa. 

For this project Hatraco has delivered 2 Hydraulic start systems designed, built and tested according to project specifications and as per NFPA-20 requirements. The system are design approved and witnessed tested By American bureau of Shipping.


 

TECHNICAL INFORMATION
Project:ZLNG
End user:Petronas
Location:Malaysia
EPCC:SHI/JGC
Start capacity:6 x 50 Liter
Start requirements :6 times 15 seconds each
Recharge time:within 15 minutes
Engine:MTU 12V4000
Required engine firing speed  :120 RPM
Application:Starting systems for MTU 12V4000 engines
Design code / Certification   :ASME VIII Div 1, U-stamped ABS certified
Specialties:ABS design approval and witnessed FAT test
  E-motor driven- and PTO driven recharge pump
  2 start valve manifolds for individual accumulator depletion