Commissioning 4 QSK95 FWP start systems

Hatraco was asked to send a Team of Engineers out to Singapore for the final commissioning of the 4 hydraulic starting systems on board of the BW Opal FPSO. Our engineers have been on board for 5 days and succeeded to do the commissioning, inspection and related testing. The systems are ready, functional and fully standby.

We wish the BW Opal many safe journeys. 


 

TECHNICAL INFORMATION
Project:BW Opal FPSO
End user:Santos
Location:Australia, Barossa field
EPCC:BW-Offshore
Start capacity:12 x 50 Litres
Start requirements :6 times, 15 seconds each
Recharge time:within 45 minutes
Engine:Cummins QSK95
Required engine firing speed  :120 RPM
Application:Cummins QSK95 diesel driven FWP
Design code / Certification   :DNV approved design drawing and witnessed FAT test
Specialties:12x50L back to back coupled accumulators
  Control panel for stand alone operation
  2 start valve manifolds for individual accumulator depletion